Water Main Replacement Projects

It Begins Beneath Your Street. Investing in Safe, Reliable Water.

Stay informed throughout the project with email or text updates and alerts

Scheduled Projects

In Progress

Portland

Brighton Ave

This project includes retirement and abandonment of around 2,800-ft of redundant undersized 6-inch cast iron water main with an extensive break history in Brighton Avenue in Portland. Services, hydrants, and water main connections that are connected to the existing 6-inch main will be moved to the existing 12-inch cast iron main on the opposite side of Brighton Avenue. This work is being completed in advance of paving by the State planned for 2028.

Contractor: Gorham Sand & Gravel
Status:
50%
Chapman Street & Fisher Street

Chapman Street & Fisher Street

This project includes installation of around 1,000-ft of ductile iron water main ranging in size from 4-inch to 8-inch in Chapman and Fisher Streets in Portland. These new mains will replace undersized 2-inch galvanized (installed 1933), 2.25-inch cast iron (installed 1951-1967), and 8-inch ductile iron (installed 1985) mains in these roads that have an extensive leak history. Project Notification Door  Hanger

Contractor: Portland Water District
Status:
85%
Ocean Avenue & Irving Street

Ocean Avenue & Irving Street

This project includes installation of around 1,100-ft of ductile iron water main ranging in size from 4-inch to 12-inch in Ocean Avenue and Sawyer Street in Portland. These new mains will replace 12-inch cast iron (installed 1911) and 6-inch cast iron (installed 1914-1917) mains in these roads.

Contractor: Pratt & Sons
Status:
90%

South Portland

Broadway & Sawyer Street

Broadway & Sawyer Street

This project includes installation of around 950-ft of ductile iron water mains ranging in size from 4-inch to 12-inch in Broadway, Sawyer Street, and Virginia Avenue in South Portland. These new mains will replace undersized 2.25-inch cast iron (installed 1952), 6-inch cast iron (1892), 8-inch cast iron (installed 1902-1904), and 12-inch cast iron (installed 1922-1931) mains in these roads, complete a 12-inch loop started in 2024 in Sawyer Street, and will be completed in advance of paving by the City planned for 2027. x

Contractor: EnerSite
Status:
50%

Westbrook

Pierce Street & Nasson Avenue

Pierce Street & Nasson Avenue

This project includes installation of around 2,380-ft of ductile iron water main ranging in size from 8-inch to 12-inch in Pierce Street and Nasson Avenue in Westbrook. The water main replacement includes installation of around 20-ft of 12-inch HDPE water main beneath an exempt railroad crossing in Pierce Street. This new main will replace undersized 6-inch cast iron (installed 1912-1963) and 8-inch cast iron (installed 1939) mains in these roads that have an extensive leak history and in advance of paving by the City planned for 2027.

Contractor: EnerSite
Status:
60%

Windham

Chute Road – River Road to Pope Road

Chute Road – River Road to Pope Road

The District will install roughly 13,500 feet of new 16-inch ductile iron water main in Chute Road from River Road to Pope Road. Project work will take place in 2025 and 2026.

Contractor: RJ Grondin
Status:
95%

Upcoming

Portland

David Road & Mayer Road

David Road & Mayer Road

This water main renewal project, in partnership with the City of Portland’s sewer and storm separation and drainage improvement project, includes the installation of approximately 1,800 feet of 8-inch ductile iron water main along David Road and Mayer Road in Portland. The new main will replace undersized 2.25-inch cast iron water main installed in 1953 and 1958, as well as 6-inch cast iron water main installed in 1953 and 8-inch cast iron water main installed in 1958. The 2.5-inch cast iron main in these roads also has an extensive history of leaks.

Contractor: To be determined
Status:

Planned for Construction in 2027

South Portland

Galvanized Pipe Replacement – Phase 1

This project includes installation of around 1,000-ft of 4-inch ductile iron and 2-inch HDPE water mains in Beach Street, Myrtle Lane, Carver Boulevard, Skillings Street, and Skyline Road in South Portland. These new mains will replace undersized 2-inch galvanized (installed prior to 1930) mains in these roads.

Contractor: Aceto Earthworks
Status:

Construction Start To Be Determined

Westbrook

County Road

This project includes installation of around 1,900-ft of 14-inch HDPE water main in County Road in Westbrook. This new main will replace 12-inch ductile iron (installed 1973) main in this road that has an extensive leak history.

Contractor: To be determined
Status:

Planned for Construction in 2027

Windham

Windham Center Road

Windham Center Road

PWD will replace roughly 1,700 feet of existing cast iron water main originally installed in 1969 in Windham Center Road with new ductile iron water main.

Contractor: Shaw Brothers
Status:

Planned for Construction in Spring 2027

Complete

Portland

Hillcrest Avenue

This project includes installation of around 200-ft of 2-inch HDPE water main in Hillcrest Avenue in Portland. This new main will replace an undersized 2-inch galvanized main (installed 1912) in this road that has an extensive leak history.

Contractor: Portland Water District
Status:
100%
Sandy Terrace

This project includes installation of around 600-ft of ductile iron water main ranging in size from 4-inch to 8-inch in Sandy Terrace in Portland. This new main will replace undersized 2.25-inch cast iron (installed 1953-1955) and 8-inch cast iron (installed 1963) mains in these roads that have an extensive leak history and in advance of paving by the City planned for 2027.  

Contractor: Hird Contracting
Status:
100%

The Portland Water District has been serving Greater Portland communities with Sebago Lake water for more than 100 years and upgrading and maintaining the system since 1908. The Portland Water District invests roughly $8 million a year in water main renewals. Since 1985, reported leaks have been reduced due to the effectiveness of this program, even with the continued aging of existing water mains.

The District’s goal with the Water Main Replacement Program is to provide a reliable distribution system designed and maintained to enhance public health and safety. Water main replacement involves replacing existing water mains with new ones to improve water flow characteristics and to improve service to our customers.

Mains are identified for replacement according to numerous criteria, including:

  • Partnering opportunities with municipal and MDOT road reconstruction and combined sewer overflow (CSO) projects
  • Opportunities to improve water quality or address water quality concerns 
  • Leak frequency
  • Aging infrastructure and/or outdated water main material
  • Critical loop feeds (eliminating dead ends based on flow characteristics)

Main replacement projects are typically scheduled for construction between April and November.

If you would like more information on these or other water main renewal projects please contact the Asset Management and Planning Group at (207) 774-5961 ext. 3199.

Frequently Asked Questions

Yes! The connection we make to your spigot will have an outlet to connect a garden hose to.

Yes! Please don’t run over the pipe!

No. PWD will only be paving the trench we cut for the water main and services.

Yes! PWD will work with the City to make sure the truck can make it down the street. If it can’t, PWD will move bins for collection. Please make sure they’re numbered!

Yes! PWD will maintain a lane and be prepared to move/make adjustments to provide immediate access to emergency vehicles.

No. All excavation will be maintained within the public right-of-way. Temporary water piping will be laid on private property to the spigot (no digging required).

If damage occurs during construction, please reach out to the PWD Project Manager. They can walk you through submitting a claim on our website.

The PWD foreman will coordinate with residents before we dig in front of your driveway. The best strategy is to park on the street when we’re coming toward your home, but we’ll knock beforehand if you’re still parked in the driveway.

Yes! The temporary water passes the same testing and is the same water we use in the rest of our system. It may be warmer than usual due to the pipe on the surface, but PWD will work to minimize that impact.

No. This project has been planned and budgeted for as part of PWD’s annual water main replacement program.