The Portland Water District has been serving Greater Portland communities with Sebago Lake water for more than 100 years and upgrading and maintaining the system since 1908. The Portland Water District invests roughly $8 million a year in water main renewals. Since 1985, reported leaks have been reduced due to the effectiveness of this program, even with the continued aging of existing water mains.

The District’s goal with the Water Main Replacement Program is to provide a reliable distribution system designed and maintained to enhance public health and safety. Water main replacement involves replacing existing water mains with new ones to improve water flow characteristics and to improve service to our customers.

Mains are identified for replacement according to numerous criteria, including:

  • Partnering opportunities with municipal and MDOT road reconstruction and combined sewer overflow (CSO) projects
  • Opportunities to improve water quality or address water quality concerns 
  • Leak frequency
  • Aging infrastructure and/or outdated water main material
  • Critical loop feeds (eliminating dead ends based on flow characteristics)

Main replacement projects are typically scheduled for construction between April and November.

Scheduled Projects

This page was last updated: 02/26/2026

Portland

Brighton Avenue

Contractor:

To be determined

Advertisement Date:

Anticipated March 2026

PWD will be removing a redundant water main Brighton Avenue between the Woodford Street intersection and the Capisic Street intersection. Water mains, hydrants, and services that are connected to the existing main from 1896 will be moved to the other existing main in Brighton Avenue.

Chapman Street & Fisher Street

Contractor:

Portland Water District

Start Date:

Anticipated construction start date June 2026

PWD will replace roughly 1000 feet of existing galvanized iron water main originally installed in 1933 in Fisher and Chapman Streets with new ductile iron water main.

Hillcrest Avenue

Contractor:

Portland Water District

Start Date:

Anticipated construction start date April 2026

PWD will replace roughly 200 feet of existing galvanized iron water main originally installed in 1912 in Hillcrest Avenue with new HDPE water main.

Ocean Avenue & Irving Street

Contractor:

Pratt & Sons

Start Date:

Anticipated construction start date April 2026

PWD will replace roughly 1,250 feet of existing cast iron water main originally installed in 1911 in Ocean Avenue and Irving Street with new ductile iron water main.

Sandy Terrace

Contractor:

To be determined

Advertisement Date:

Bids Received

PWD will replace roughly 700 feet of existing cast iron water main originally installed in 1953 in Sandy Terrace with new ductile iron water main.

South Portland

Broadway & Sawyer

Contractor:

To be determined

Advertisement Date:

Anticipated March 2026

PWD will replace roughly 750 feet of existing cast iron water main originally installed in 1953 in Broadway and Sawyer Street with new ductile iron water main.

Galvanized Pipe Replacement – Various Streets

Contractor:

TBD

Advertisement Date:

Anticipated March 2026

PWD will replace roughly 1,000 feet of existing galvanized iron water main originally installed prior to 1930 in Beach Street, Myrtle Avenue, Carver Boulevard, Skillings Street, and Skyline Road with new HDPE and ductile iron water main.

Westbrook

County Road

Contractor:

To Be Determined

Advertisement Date:

Anticipated March 2026

PWD will replace roughly 1,900 feet of existing ductile iron water main originally installed in 1973 in County Road with new HDPE water main.

Pierce Street & Nasson Avenue

Contractor:

To Be Determined

Advertisement Date:

Project Advertised

PWD will replace roughly 2,225 feet of existing cast iron water main originally installed in 1912 in Pierce Street and Nasson Avenue with new ductile iron water main.

Windham

a map showing chute road in windham

Chute Road – River Road to Pope Road

Contractor:

RJ Grondin

Completion:

15%

The District will install roughly 13,500 feet of new 16-inch ductile iron water main in Chute Road from River Road to Pope Road. Project work will take place in 2025 and 2026.

Windham Center Road

Contractor:

To Be Determined

Advertisement Date:

Project Advertised

PWD will replace roughly 1,700 feet of existing cast iron water main originally installed in 1969 in Windham Center Road with new ductile iron water main.

If you would like more information on these or other water main renewal projects please contact the Asset Management and Planning Group at (207) 774-5961 ext. 3199.