PROJECTS SCHEDULED FOR 2023
(click on map for larger view)
|
CAPE ELIZABETH |
 |
Oakhurst Neighborhood Area Main Replacement – Hermit Thrust Road and Glenden Road
Contractor: Bowdoin Excavation
The District is replacing 1,000 feet of 1940 Galvanize pipe on Hermit Thrust and Glenden Road.
|
Project Status: - 100% Complete |
GORHAM |
 |
Sebago Lake Road - Justice Way to Huston Road
Contractor: Gorham Sand and Gravel
The District will replace roughly 1,300 feet of 12-inch cast iron and ductile iron water main originally installed in 1953 and 1980 respectively with new 12-inch ductile iron water main.
|
Project Status: - 90% Complete |
 |
Highland Avenue Ext - Lincoln Street to Dead End
Contractor: Gorham Sand & Gravel
The District is replacing 240 feet of 2”-1933 Galvanize pipe on Highland Ave Ext.
|
Project Status: - 100% Complete |
 |
Old Oak Lane – New Portland Rd to Dead End
Contractor: Gorham Sand & Gravel
The District is replacing 350 feet of 2” - 1939 Galvanize pipe on Old Oak Lane.
|
Project Status: - 100% Complete |
 |
Douglas Street – Morrill Ave to Corner
Contractor: Gorham Sand & Gravel
The District is replacing 160 feet of 2” -1955 Galvanize pipe on Douglas Street.
|
Project Status: - 100% Complete |
PORTLAND |
 |
Forest Avenue - Somerset St to Park Ave
Contractor: Gorham Sand & Gravel
The District will replace roughly 375 feet of 12-inch cast iron water main originally installed in 1886 with new 8-inch ductile iron water main.
|
Project Status: - 30% Complete |
 |
Great Diamond – Little Diamond Island Submerged Water Main
Contractor: R.E. Coleman
The District will replace roughly 2160 feet of 8-inch cast iron water main originally installed in 1955 and 1956 with new 14-inch HDPE and 12-inch ductile iron water main.
|
Project Status: - 10% Complete |
 |
Holm Avenue / Barron Center
Contractor: Glidden
The District will replace 1,600 feet of old undersized 1931 - 8” cast iron with new 12” ductile iron pipe through the Barron Center property to Holm Ave and along Holm Ave to Forest Avenue.
|
Project Status: - 100% Complete |
SCARBOROUGH |
 |
Piper Road (Piper Shores)
Contractor: Grondin Corporation
The District will replace roughly 500 feet of 8-inch ductile iron water main originally installed in 2000 with new 8-inch PVC water main.
|
Project Status: - 100% Complete |
SOUTH PORTLAND |
 |
Craggmere Avenue - Cottage Rd to Lahave St.
Contractor: R. E. Coleman
The District will replace roughly 750 feet of 2-inch galvanized iron water main originally installed in 1938 with new 6-inch ductile iron water main.
|
Project Status: - 95% Complete |
 |
S. Marriner Street & Cobb Street
Contractor: DLM Property Care
The District will replace roughly 200 feet of 2-inch galvanized iron water main originally installed in 1933 and 1942 with new 8-inch ductile iron water main.
|
Project Status: - 50% Complete |
 |
City Service Road - Off of Highland Ave
Contractor: Grondin Corporation
The District will replace roughly 950 feet of 8-inch ductile iron water main originally installed in 1981 with new 8-inch PVC water main.
|
Project Status: - 100% Complete |
WESTBROOK |
 |
Seavey Street - Main St to Rochester St
Contractor: Pratt & Sons
The District will replace roughly 1,700 feet of 6-inch cast iron water main originally installed in 1889 with new 8-inch ductile iron water main.
|
Project Status: - 50% Complete |
 |
Duck Pond Road - North entrance at Route 302 - 2,200 ft. to the east
Contractor: Gorham Sand & Gravel
The District will replace 2,200 feet of old 1961 - 10” cast iron with multiple leaks with new 12” ductile iron pipe.
|
Project Status: - 100% Complete |
WINDHAM |
 |
Main Street - Depot Street to River Road
Contractor: TBD
The District will replace 3,600 feet of old 1952 - 8” cast iron with multiple leaks with new 16” ductile iron pipe.
|
Project Status: - Start Spring of 2024
|
 |
High Street - Depot Street to Holly Lane
Contractor: RJ Grondin
The District will replace 1,000 feet of old 1913 - 8” cast iron with new 8” ductile iron pipe.
|
Project Status: - 100% Complete |