SCHEDULED PROJECTS
(click on map for larger view)
|
FALMOUTH |
|
Falmouth Road at Winn Road
Contractor: R.E. Coleman
The District will replace roughly 1,200 feet of 8-inch ductile iron and 12-inch cast iron water main originally installed in 1989 and 1954 in Falmouth Road and Winn Road with new 8-inch PVC water main.
|
Construction 100% Complete |
PORTLAND |
|
Dennett Street & Donald Street
Contractor: TBD
The District will replace roughly 570 feet of 2.25-inch Cast Iron water main originally installed in 1953 in Dennett and Donald Streets with new 8-inch and 4-inch ductile iron water main. Project work will take place in 2025.
|
Anticipated Advertisement Late 2024
|
|
Dorset Street - Brighton Avenue to Dead End
Contractor: Aceto Earthworks
The District will replace roughly 1,400 feet of 2.25-inch cast iron originally installed between 1954 and 1955 in Dorest Street with 8-inch ductile water main.
Construction 5% Complete
|
Construction 5% Complete |
|
Elizabeth Road Transmission Valves
Contractor: TBD
The District will replace two large diameter transmission main valves in Elizabeth Road as well as associated small and large diameter water mains. Project work will take place in 2025.
|
Anticipated Advertisement Late 2024 |
|
Elm Street - Somerset Street to Oxford Street
Contractor: Gorham Sand and Gravel
The District will replace roughly 800 feet of 4-inch and 6-inch cast iron water main originally installed in 1880, 1887, and 1891 in Elm Street with new 8-inch ductile iron water main.
|
Construction 67% Complete |
|
Hersey Street - Ocean Avenue to Clifton Street
Contractor: TBD
The District will replace roughly 1,500 feet of 8-inch cast iron water main originally installed in 1931 & 1934 in Hersey Street with new 8-inch ductile iron water main.
|
Planned for Spring 2025 |
|
Kent Street
Contractor: TBD
The District will replace roughly 640 feet of 2.25-inch cast iron water main originally installed in 1955 in Kent Street between Riggs Street and Brighton Avenue with new 6-inch cast iron water main. Project work will take place in 2025.
|
Anticipated Advertisement Late 2024 |
|
Providence Street
Contractor: TBD
The District will replace roughly 1,940 feet of 12-inch cast iron water main originally installed in 1927 in Providence Street between Ocean Avenue and Presumpscot Street with new 12-inch ductile iron water main. Project work will take place in 2025.
|
Anticipated Advertisement Late 2024 |
|
Vaill Street, Olympia Street, & Helene Street
Contractor: Portland Water District
The District will replace roughly 900 feet of 2.25-inch cast iron water main originally installed in 1955 and 1966 in Vaill Street, Olympia Street, and Helene Street with new 4-inch ductile iron water main
|
Construction 100% Complete |
|
Western Promenade, Vaughan Street & Danforth Street
Contractor: D&C Construction
The District will replace roughly 600 feet of 2.25-inch cast iron and 12-inch cast iron water main originally installed in 1951 and 1930 in Western Promenade, Vaughan Street, and Danforth Streets with new 4-inch and 12-inch ductile iron water main.
|
Construction 100% Complete |
SOUTH PORTLAND |
|
Galvanized Pipe Replacement - Various Streets*
Contractor: TBD
The District will replace roughly 2,500 feet of 2-inch galvanized iron water main originally installed prior to 1930 in Beach Street, Burwell Avenue, Carver Boulevard, Day Street, Grand Street, Myrtle Avenue, Skillings Street, Skyline Drive, and Vincent Street with new water main of varying sizes and materials. Project work will take place in 2025 and 2026.
* -This project also includes scope in Westbrook
|
Anticipated Advertisement Early 2025 |
|
Market Street ROW, Thomas Street ROW
Contractor: Gorham Sand and Gravel
The District will replace roughly 1,000 feet of 8-inch cast iron water main originally installed in 1958 and 1965 in Market Street ROW and Thomas Street ROW with new 8-inch ductile iron and HDPE water main.
|
Construction 100% Complete |
|
Sawyer Street - Front Street to Broadway
Contractor: Glidden Excavating & Paving
The District will replace roughly 3,000 feet of 6-inch cast iron water main originally installed in 1892 in Sawyer Street with new 12-inch ductile iron water main.
|
Construction 67% Complete |
WESTBROOK |
|
Galvanized Pipe Replacement - Libby & Forest*
Contractor: TBD
The District will replace roughly 1,060 feet of water main of various sizes and materials in Libby Avenue and Forest Street with new 8-inch ductile iron water main. Project work will take place in 2025 and 2026.
* -This project also includes scope in South Portland
|
Anticipated Advertisement Early 2025
|
WINDHAM |
|
Chute Road - River Road to Pope Road
Contractor: TBD
The District will install roughly 13,500 feet of new 16-inch ductile iron water main in Chute Road from River Road to Pope Road. Project work will take place in 2025 and 2026.
|
Anticipated Advertisement Late 2024 |
|
Main Street - Depot Street to River Road
Contractor: Shaw Brothers / Gorham Sand & Gravel
The District will replace 3,600 feet of old 1952 - 8” cast iron with multiple leaks with new 16” ductile iron pipe.
|
Construction 90% Complete
|