Water Main Replacement Program
Sandy Terrace
Description
Project Manager
Sarah Payne
Contractor
Hird Contracting
Project Updates
Status
Project Timeline
Project Committed
September 1, 2025
Project Advertised
January 23, 2026
Project Awarded
March 9, 2026
Construction Begins
April 8, 2026
Temporary Water Installed
April 15, 2026
Water Main Installation Complete
May 6, 2026
Water Services Installation Complete
May 12, 2026
Temporary Water Removed
May 20, 2026
Paving Complete
May 22, 2026
Final Restoration Complete
May 28, 2027
