Water Main Replacement Program

Sandy Terrace

Status

100%
  • Get Alerts

Project Phases & Updates

Completed phase

Project Committed

September 1, 2025

Completed phase

Project Advertised

January 23, 2026

Completed phase

Project Awarded

March 9, 2026

Completed phase

Construction Begins

April 8, 2026

Completed phase

Temporary Water Installed

April 15, 2026

Completed phase

Water Main Installation Complete

May 6, 2026

Completed phase

Water Services Installation Complete

May 12, 2026

Completed phase

Temporary Water Removed

May 20, 2026

Completed phase

Paving Complete

May 22, 2026

Final Restoration Complete

May 28, 2027

Attachments

No attachments found.

Description

This project includes installation of around 600-ft of ductile iron water main ranging in size from 4-inch to 8-inch in Sandy Terrace in Portland. This new main will replace undersized 2.25-inch cast iron (installed 1953-1955) and 8-inch cast iron (installed 1963) mains in these roads that have an extensive leak history and in advance of paving by the City planned for 2027.  

Project Manager

Sarah Payne

Contractor

Hird Contracting

Project Updates

Status

100%
  • Get Alerts

Project Timeline

Completed phase

Project Committed

September 1, 2025

Completed phase

Project Advertised

January 23, 2026

Completed phase

Project Awarded

March 9, 2026

Completed phase

Construction Begins

April 8, 2026

Completed phase

Temporary Water Installed

April 15, 2026

Completed phase

Water Main Installation Complete

May 6, 2026

Completed phase

Water Services Installation Complete

May 12, 2026

Completed phase

Temporary Water Removed

May 20, 2026

Completed phase

Paving Complete

May 22, 2026

Final Restoration Complete

May 28, 2027