Water Main Replacement Program

Galvanized Pipe Replacement – Phase 1

Status

Construction Start To Be Determined

  • Get Alerts

Project Phases & Updates

Attachments

No attachments found.

Description

This project includes installation of around 1,000-ft of 4-inch ductile iron and 2-inch HDPE water mains in Beach Street, Myrtle Lane, Carver Boulevard, Skillings Street, and Skyline Road in South Portland. These new mains will replace undersized 2-inch galvanized (installed prior to 1930) mains in these roads.

Project Manager

Adam Sellick

Contractor

Aceto Earthworks

Status

Construction Start To Be Determined