Water Main Replacement Program
Construction Project Template
Description
Project Manager
Adam Sellick
Contractor
EnerSite
Project Updates
July 8, 2026
Work on the project is planned to begin Monday, July 13th.
Status
Project Timeline
Project Committed
Project Advertised
March 18, 2026
Project Awarded
April 16, 2026
Temporary Water Installed
July 27, 2026
Water Main Installation Complete
October 2, 2026
Water Services Installation Complete
October 2, 2026
Temporary Water Removed
October 9, 2026
Paving Complete
October 16, 2026
Final Restoration Complete
May 28, 2027
