Water Main Replacement Program
Construction Project Template
Description
This project includes installation of around 600-ft of ductile iron water main ranging in size from 4-inch to 8-inch in Sandy Terrace in Portland. This new main will replace undersized 2.25-inch cast iron (installed 1953-1955) and 8-inch cast iron (installed 1963) mains in these roads that have an extensive leak history and in advance of paving by the City planned for 2027.
Project Manager
Sarah Payne
Contractor
Hird Contracting