Water Main Replacement Program

Construction Project Template

Status

40%
  • Get Alerts

Project Phases & Updates

Attachments

No attachments found.

Description

This project includes installation of around 600-ft of ductile iron water main ranging in size from 4-inch to 8-inch in Sandy Terrace in Portland. This new main will replace undersized 2.25-inch cast iron (installed 1953-1955) and 8-inch cast iron (installed 1963) mains in these roads that have an extensive leak history and in advance of paving by the City planned for 2027.  

Project Manager

Sarah Payne

Contractor

Hird Contracting

Status

85%
  • Get Alerts