Project Description:
In conjunction with the City of South Portland Combined Sewer Overflow Project , the Water District will be replacing old undersized water mains in the Pleasendale area and a 1912 12” cast iron pipe on Broadway from Anthoine Street to Elm. Approximately 8,200 feet of new water main will be installed as part of this project.
Contractor:
Gorham Sand & Gravel
Estimated Construction Schedule:
April - November 2018
Traffic Control
Two way traffic will be maintained on Broadway for the duration of the project. In the Pleasantdale area, streets may be closed on occasion but will allow local traffic through.
Temporary Service
All customers abutting the project will be on temporary service for the duration of the project. If a planned temporary water service shut-off is required, affected residents will be notified 48 hours in advance.
PWD Project Engineer
William E.(Ned) Pierce P.E.
Phone: 207-774-5961 ext. 3043
Email: npierce@pwd.org