The 2010 water main renewal season is now upon us. Water main renewals
involve replacing existing water mains with new ones to improve water flow
characteristics and to improve service to our customers. The following
projects are scheduled to be completed during the 2010 construction period,
April 15, 2010 - November 15, 2010. This schedule is
subject to change. Due to variables within the system, specific projects could
be postponed and others may be added.
Water mains on the renewal list usually meet 4 out of the 5 criteria
listed below.
|
1. Water Quality
2. Leak Frequency
3. Age and Type of Main
4. Municipal and M.D.O.T. Road Reconstruction
5. Critical Loop Feeds (Eliminating Dead Ends
Based on Flow Characteristics)
|
Click on an individual project to find out more information about
the proposed work planned by the Portland Water District.
A Street |
Portland |
Bid Phase |
245' |
8" |
6" |
1892 |
Cole Street |
Falmouth |
Bid Phase |
340' |
4" |
2.25" |
1958 |
Gilman Street |
Porltand |
Bid Phase |
895' |
8" |
6" |
1932 |
Marston Street |
Falmouth |
Bid Phase |
490' |
4" |
2" |
1955 |
Oriole Street |
Falmouth |
Bid Phase |
225' |
4" |
2.25" |
1957 |
Willow Street |
Peaks Island |
Design Complete |
720' |
4" |
2" |
1926 |
|
|
|
|
|
|
|
|
|
Combined with City of Portland Projects |
Allen Avenue |
Portland |
Construction Phase |
700' |
8" |
8" |
1923 |
Bell Street |
Portland |
Design Phase |
150' |
12" |
12" |
1928 |
Canco Road |
Portland |
Design Phase |
670' |
8" |
6" |
1938 |
Canco Road |
Portland |
Construction
Phase |
515' |
8" |
6" |
1938 |
Capisic Street |
Portland |
Bid Phase |
900' |
8" |
8" |
1954 |
Carlyle Road |
Portland |
Design Phase |
1,650' |
8" |
6" |
1938 |
Drake Street |
Portland |
Construction
Phase |
380' |
4" |
1.25" |
1978 |
Gleckler Road |
Portland |
Construction
Phase |
720' |
8" |
6" |
1938 |
Lowell Street |
Portland |
Construction
Phase |
520' |
8" |
6" |
1910 |
Macy Street |
Portland |
Bid Phase |
400' |
4" |
2" |
1913 |
Read Street |
Portland |
Design Phase |
1,700' |
8"-12" |
6"-8" |
1897-1927 |
Walton Street |
Portland |
Design Phase |
780' |
8" |
6" |
1886 |
Washington Ave |
Portland |
Construction
Phase |
700' |
8" |
6" |
1897 |
Wellington Rd |
Portland |
Construction
Phase |
1,670' |
8" |
6" |
1939-1957 |
|
|
|
|
|
|
|
|
|
Combined with City of Westbrook Projects |
Doyle Street |
Westbrook |
Design Phase |
465' |
4" |
2.25" |
1971 |
Highland Street |
Westbrook |
Design Phase |
340' |
4" |
2.25" |
1971 |
Pleasant Street |
Westbrook |
Design Phase |
625' |
8" |
6" |
1933 |
Sargent Street |
Westbrook |
Design Phase |
720' |
4"-8" |
6"-2.25" |
1915-1954 |
Stroudwater St |
Westbrook |
Design Phase |
200' |
8" |
6" |
1894 |
|
|
|
|
|
|
|
|
|
Combined with Town of Scarborough Projects |
Old County Rd |
Scarborough |
Construction
Phase |
520' |
8" |
8" |
1970 |
|
|
|
|
|
|
|
|
| |
|
|
| |
The Portland Water District has been serving Greater Portland communities
with Sebago Lake water for more than 100 years and upgrading and maintaining the
system since 1908. For the past several years, the Portland Water District has
invested roughly $2 million dollars a year in water main renewals. Since 1985,
reported leaks have been reduced by roughly 30 percent due to the effectiveness
of this program, even with the continued aging of existing water mains.
If you would like more information on the water main renewal projects please
contact Asset Management and Planning Group at
(207) 774-5961 extension 3043.
For more information on projects, visit The City of Portland's Web Site.
|