Doyle St:
Replace approximately 465ft of existing 2.25" ductile iron
(1971) water main under Doyle St with 4" ductile iron.
Includes replacement of line on Highland Ct.
Highland St:
Replace approximately 340ft of existing 2.25" cement lined cast
iron (1971) water main under Highland St with 4" ductile iron.
Pleasant St:
Replace approximately 625ft of existing 6" cast iron water main
(1933) with 8" ductile iron water main under Pleasant St
starting at Stroudwater.
Sargent St:
Replace approximately 300ft of existing 8" cast iron from
Pleasant St with 8"ductile iron. Replace the remaining
420ft of existing 4" cast iron water main with 4" ductile iron.