- Bell Ave:
Replace approximately 150ft of existing 12" main under Bell Ave.
Replacement pipes will be 12" cast iron south of Read St. and
12" ductile iron north of
Read St. Start Date: March 24, 2011
- Read St:
Replace approximately 540 feet of existing 6" ductile iron main
with 8" between Forest Ave and Bell St. Also, replacing
approximately 1160 feet of existing 8" ductile iron main with
12" starting at the intersection of Read and Bell Rd. Start
Date: April 21, 2011
- Canco Rd:
Replace approximately 515ft of existing 6" ductile iron
with 8" between Wellingtion and Walton Rd. Start Date: October
10, 2010
- Carlyle Rd:
Replace approximately 1,650ft of existing 6" cast iron under all
of Carlyle Rd with 8" pipe. Start Date: October 7, 2010
- Walton Rd:
Replace approximately 780ft of existing 6" cast iron with
8" between the intersection of Canco Rd and the intersection of
Forest Ave. Start Date: March 15, 2011
Updated 11/9/11
|