Bid Package Bellevue St

MAPS
 Community Portland
 Status Complete
 Total Feet 4170'
 New Size 6":12"
 Exist. Size 12" and 8"
 Vintage 1897-1928, 1938
 Bid Cost $863,200.00
 Contractor Dearborn Brothers Construction
 Start Date 10/7/10
 Project Notice Letter Notice to Abutters
 Completion Date 9/8/11
Bell / Read St
Canco/ Carlyle/ Walton Rd
Back
 

 

  • Bell Ave:
    Replace approximately 150ft of existing 12" main under Bell Ave.  Replacement pipes will be 12" cast iron south of Read St. and 12" ductile iron north of Read St. Start Date: March 24, 2011
     
  • Read St:
    Replace approximately 540 feet of existing 6" ductile iron main with 8" between Forest Ave and Bell St. Also, replacing approximately 1160 feet of existing 8" ductile iron main with 12" starting at the intersection of Read and Bell Rd. Start Date: April 21, 2011
     
  • Canco Rd:
    Replace approximately 515ft of existing 6" ductile iron with 8" between Wellingtion and Walton Rd. Start Date: October 10, 2010
     
  • Carlyle Rd:
    Replace approximately 1,650ft of existing 6" cast iron under all of Carlyle Rd with 8" pipe. Start Date: October 7, 2010
     
  • Walton Rd:
    Replace approximately 780ft of existing 6" cast iron with 8" between the intersection of Canco Rd and the intersection of Forest Ave. Start Date: March 15, 2011

 

Updated 11/9/11