Spring Street

 

Map
Back
 
 Community Westbrook
 Status Under Construction
 Feet 590'
 New Size 8"
 Exist. Size 6" Cast Iron
 Vintage 1889
 Bid Cost $ 307,075.00
 Contractor R. J. Grondin & Sons, Inc.
 Start Date 6/15/2009
 Project Notice Letter  
 Completion Date 9/4/2009

 

Project involves the renewal of 590' of existing 6" cast iron in Spring Street with new 8" ductile iron as shown in the attached map.  This project will be undertaken due to the age and type of main as well as improve water quality.

This project is in conjunction with the Stroudwater Street and Pleasant Street water main replacements.

CLICK ON THE MAP BUTTON FOR THE LIMITS OF THIS PROJECT