East Bridge Street

 

Map
Back
 
 Community Westbrook
 Status Under Construction
 Feet 2205'
 New Size 12" PVC (C900)
 Exist. Size 12" Ductile Iron
 Vintage 1974 / 1977
 Bid Cost $817,435.00
 Contractor Glidden Excavation & Paving
 Start Date 6/1/2009
 Project Notice Letter Click Here for Project Notification Letter
 Completion Date 9/4/2009

 

Project involves the renewal of 2205' of existing 12" ductile iron water main with new 12" PVC (C900) pipe.  The location of this project is on East Bridge Street from Bridgton Road (Route 302) to Carlson Street, as shown on the attached map.  This project will be undertaken due to the high amount of leaks on this segment of water main.

This project is in conjunction with Main Street, Berkeley Street, and Oak Street water main replacements.

CLICK ON THE MAP BUTTON FOR THE LIMITS OF THIS PROJECT