Clifton Street

 

Map
Back
 
 Community Portland
 Status Under Construction
 Feet 2515' of 8" / 1240' of 4"
 New Size 8" Ductile Iron
 Exist. Size 8" Cast Iron
 Vintage 1934
 Bid Cost $359,187.05
 Contractor Storey Brothers
 Start Date 7/1/2009
 Project Notice Letter Click Here for Project Notification Letter
 Completion Date 9/30/2009

 

The location of this project is on Clifton Street from Vannah Avenue to Pya Road, as shown on the attached map. Project involves the renewal of 2,515' of existing 8" cast iron water main with new 8" ductile iron.  This project also involves the renewal of 1,240' of existing water main with new 4" ductile iron on Hersey Street, Codman Street, Chenery Street, Bayview Drive, Parsons Road, Mackworth Street, Austin Street, George Street and Pya Road. 

This project will be undertaken due to the age and type of main as well as the high amount of leaks on this segment of cast iron pipe.

CLICK ON THE MAP BUTTON FOR THE LIMITS OF THIS PROJECT